190MW CCPP in Malaysia, located in Api, provincial capital of Sabah, is a thermopower plant devoting in mitigating power shortage in east Malaysia. The construction term is 26 months.
CNEEC undertook the EPC contracting such as design, supply, construction, installation and testing. The power plant was composed of two gas turbo-generator units, two waste heat boilers, one steam generator unit, with a net output of 190MW.
ADD : CNEEC BLDG., 9, SOUTH SHOUTI RD., HAIDIAN DISTRICT, BEIJING 100048 P.R.CHINA
TEL : (8610)68798899
FAX : (8610)68798000
E-MAIL : cneec@cneec.com.cn